Roles, Responsibilities & Management Products (PRINCE2 7 Practitioner)  Flashcards

PRINCE2 7 Practitioner Flashcards

FrontBack
Give an example of RACI for delivering a work packageTeam Manager Responsible Project Manager Accountable Project Assurance Consulted User Representative Informed Project Board
What does a Team Manager doManages the delivery of assigned work packages and ensures products are created to quality criteria
What does RACI stand forResponsible Accountable Consulted Informed
What does the Executive doProvides business leadership ensures value for money and is answerable for benefits and overall success
What does the Senior Supplier doRepresents the suppliers and ensures that solutions are feasible and can be supplied within constraints
What is a Checkpoint ReportReport from Team Manager to Project Manager detailing progress and issues for specific work packages
What is a Highlight ReportPeriodic report from the Project Manager to the Project Board summarizing progress and issues
What is a Product DescriptionDefines the purpose composition quality criteria and acceptance method for a product
What is a Project PlanPresents how objectives will be delivered defines time cost scope and major controls for the project
What is a Project Product DescriptionDefines the project's final product acceptance criteria purpose and who will use it
What is a Stage PlanMore detailed plan for a single stage that guides day to day stage delivery and monitoring
What is a Team PlanPlan used by the team to manage production of products and to estimate resource needs
What is a Work PackageDocument that specifies products quality criteria timescales and tolerances for a team to deliver
What is an Exception ReportProduced when tolerances are forecast to be exceeded proposing corrective action or escalation
What is Project AssuranceIndependent oversight of project performance and products to protect stakeholder interests
What is Project SupportProvides administrative help configuration control and support tools to the project manager and team
What is the Benefits Management ApproachDescribes how benefits will be measured tracked and realized after project closure
What is the Business CasePresents rationale costs benefits risks and timescales and justifies the project investment
What is the Change AuthorityDelegated role to approve changes within set limits to speed up change control decisions
What is the Change Control ApproachDefines how changes are identified assessed authorized and implemented during the project
What is the Communication Management ApproachOutlines stakeholder information needs frequency channels and responsibilities for communications
What is the Configuration Item RecordTracks configuration items status history and version control for product integrity
What is the End Project ReportSummarizes overall project performance outcomes benefits achieved and lessons for future projects
What is the End Stage ReportProvides stage performance assessment and recommends whether to continue to the next stage
What is the Issue LogRecord of requests problems and changes and the actions taken to resolve them
What is the Lessons LogRecords lessons learned for use during the project and for future projects improvement
What is the Project Initiation Documentation PIDPID compiles Business Case plan controls organization and baselines to authorize project execution
What is the Project Manager responsible forDay to day management of the project plans controls risks issues quality and reports to the Project Board
What is the purpose of the Daily LogUsed by the Project Manager to record informal issues actions and day to day decisions
What is the Quality Management ApproachDescribes quality methods acceptance criteria and responsibilities to ensure fitness for purpose
What is the Quality RegisterLists planned quality activities and records results to demonstrate product acceptance
What is the Risk RegisterLog of identified risks their assessments and planned responses to manage uncertainty
What is the role of the Project BoardOwns the project and is accountable for investment decisions approves major plans and sets tolerances
What is the role of the Senior UserRepresents user needs and acceptance ensures the project will meet user requirements and realise benefits
Who approves exception plansThe Project Board approves exception plans when tolerances are forecast to be exceeded
Who is accountable for the Business CaseThe Project Board owns and is accountable for the Business Case and benefits justification
Who is responsible for product deliveryTeam Managers are responsible for delivering products to the quality expectations in their work packages
Who is responsible for quality assuranceProject Assurance monitors and verifies quality independent of the delivery team
Why are tolerances importantThey allow delegated control and define limits of variance that avoid unnecessary escalation
Why does the PID matterIt establishes the baseline for authority scope and control and provides a single source of project information
Why is risk management keyProactive risk management reduces threats increases opportunities and protects delivery of objectives
Why is the Business Case importantIt drives decisions and determines whether the project should start continue or close
Why maintain baselinesBaselines provide controlled reference points for scope time cost and configuration to manage change
Focuses on project board and team roles, accountability, RACI-type interactions, and the main management products (plans, logs, reports), including what each product contains and why it matters.