Bash, the Crucial Exams Chat Bot
AI Bot

Processes and Workflow (PRINCE2 7 Practitioner)  Flashcards

PRINCE2 7 Practitioner Flashcards

FrontBack
Define Managing Product Delivery objectiveEnsure products are created and delivered to agreed quality time and cost
Exam tip How to recall process responsibilities quicklyRemember who owns decisions Project Board owns direction Project Manager controls stages Team Manager delivers products
How are tolerances used in PRINCE2Set limits for time cost scope risk and quality allowing management without escalation within tolerances
Key activities in Controlling a StageAuthorize work packages review progress manage issues escalate to board and report via highlight reports
Key activities in Starting Up a ProjectAppoint executive and project manager capture lessons create project brief and prepare initiation stage plan
List the seven PRINCE2 processes in logical sequenceStarting Up a Project Directing a Project Initiating a Project Controlling a Stage Managing Product Delivery Managing a Stage Boundary Closing a Project
Name the key contents of the PIDBusiness Case Project Plan Risk and Quality approaches Controls and Baseline
Role of the Change AuthorityAuthorize changes within delegated tolerances and decide on requests for change
Typical flow for a Work Package Start to FinishCreated in Controlling a Stage delegated to Managing Product Delivery executed returned and accepted
What are the outputs of Managing a Stage BoundaryUpdated Project Plan Stage Plan End Stage Report and recommendation to board
What are the project board decision points during the projectAuthorize initiation authorize each stage give ad hoc direction and authorise closure
What decision does the Project Board make after Starting Up a ProjectAuthorize initiation or reject the project
What decision does the Project Board make at project closureAccept project deliverables or request follow up work and formally close the project
What does the Project Board need to review when authorizing a new stageBusiness Case End Stage Report and updated Project Plan with tolerances
What is a Highlight ReportPeriodic summary for the Project Board of progress issues and forecasted stage status
What is a Work PackageSpecification of products activities and tolerances delegated to a team manager
What is an Exception and when is it escalatedWhen tolerances are forecast to be exceeded the issue becomes an exception and is escalated to the board
What is configuration management roleControl of product versions baselines and records held in the Configuration Item Records
What is the format and purpose of an Issue RegisterRecord and track reported issues and decisions including change requests and risks
What is the main objective of Initiating a ProjectEstablish solid foundations for the project in a PID including Business Case and controls
What is the objective of Closing a ProjectConfirm acceptance of products evaluate outcomes capture lessons and close the project formally
What is the objective of Controlling a StageManage day to day delivery within a stage to keep the project on track
What is the objective of Starting Up a ProjectEnsure a valid and viable project brief exists and appoint key roles so the project can be initiated
What is the process sequence when a team completes a Work PackageTeam Manager hands over products to Project Manager who updates registers and reports to board
What is the purpose of Directing a ProjectProvide overall direction and authorize project initiation authorise stages and project closure
What is the purpose of the Lessons LogCapture lessons during project for use in current and future projects to improve performance
What management products flow from Initiating a Project to Controlling a StagePID Project Plan and initial Risk Register
What triggers a Stage Boundary processEnd of a management stage and need to plan next stage or request project closure
What triggers Directing a Project interactionsRequests for authorisation stage end exceptions and initiation and closure approvals
When is an End Stage Report producedAt the end of each management stage to inform decision on next stage
Where is the Business Case maintained and updatedThe Project Manager maintains the Business Case with changes approved by the Project Board
Which process creates the End Stage ReportManaging a Stage Boundary produces the End Stage Report to inform the board
Which process handles quality checking and acceptance of productsManaging Product Delivery performs quality checks and hands over products to project manager
Who appoints team managers and defines work packagesProject Manager issues Work Packages to Team Managers and monitors delivery
Who is responsible for overall project investment decisionProject Board Executive role holds ultimate accountability for Business Case
Who produces the Stage Plan and who approves itProject Manager produces Stage Plan Project Board approves or requests changes
Maps the seven PRINCE2 processes, their objectives, key activities, decision points, and typical management product flows to help you recall process responsibilities and sequence under exam conditions.
Share on...
Follow us on...