PRINCE2 7 Processes (Foundation) Flashcards

PRINCE2 7 Foundation Flashcards

Study our PRINCE2 7 Processes (Foundation) flashcards for the PRINCE2 7 Foundation exam with 41+ flashcards. View as flashcards, a searchable table, or as a fun matching game.
PRINCE2 7 Foundation Course Header Image
FrontBack
Closing a Project key management productsProject Closure Report Lessons Log Follow On Action Recommendations Benefits Review Plan
Closing a Project main activitiesConfirm benefits acceptance complete handover evaluate performance update logs and archive management products
Closing a Project objectiveConfirm acceptance of products capture lessons and formally close the project
Closing a Project transition pointDeliver Project Closure Report to Project Board to obtain project closure approval
Controlling a Stage key management productsWork Packages Highlight Reports Issue Reports End Stage Report
Controlling a Stage main activitiesAuthorize work packages monitor progress manage issues and risks report to Project Board
Controlling a Stage objectiveManage day to day delivery of the stage by the Project Manager to meet stage plan
Controlling a Stage transition pointPrepare End Stage Report to trigger Managing a Stage Boundary
Directing a Project key management productsProject Authorization Stage Authorization Exception Authorization End Project Authorization
Directing a Project main activitiesAuthorize initiation authorize stages provide ad hoc direction and authorize closure
Directing a Project objectiveProvide overall direction decision making and accountability from the Project Board
Directing a Project transition pointAuthorize Initiation and subsequent Stage Authorizations based on reports from the Project Manager
Initiating a Project key management productsProject Initiation Documentation Business Case Risk Register Quality Management Strategy
Initiating a Project main activitiesDevelop PID set tolerances create detailed plans update Business Case and management strategies
Initiating a Project objectiveEstablish a sound foundation by creating the Project Initiation Documentation PID
Initiating a Project transition pointPID submitted to Project Board for Authorize Project and to set baselines
Managing a Stage Boundary key management productsEnd Stage Report Next Stage Plan Updated PID Exception Plan if required
Managing a Stage Boundary main activitiesReview stage performance update Business Case prepare next Stage Plan and report issues
Managing a Stage Boundary objectivePlan the next stage update plans and seek Project Board approval to continue
Managing a Stage Boundary transition pointSubmit Next Stage Plan and End Stage Report to Project Board for Authorize Next Stage
Managing Product Delivery key management productsWork Package Product Descriptions Completed Products Quality Records
Managing Product Delivery main activitiesAccept Work Package execute work produce products perform quality checks and handover
Managing Product Delivery objectiveEnsure that agreed products are created and handed over to required quality within Work Packages
Managing Product Delivery transition pointDeliver products and notify Project Manager who updates reports and controls
Start Up a Project key management productsProject Brief Outline Business Case Project Approach Appointments
Start Up a Project main activitiesAppoint project management team capture customer needs prepare Project Brief and initial Business Case
Start Up a Project objectiveEstablish project viability and create the Project Brief
Start Up a Project transition pointSubmit Project Brief to Project Board for Authorize Initiation
What is a Highlight ReportA periodic summary of stage status issues and progress sent by the Project Manager to the Project Board
What is a Work PackageA set of information issued to a Team Manager specifying products quality criteria and tolerances
What is an End Stage ReportA report by the Project Manager summarising stage performance issues and recommendations for the Project Board
What is an Exception ReportA report raising project performance outside tolerances requesting Board direction or approval
What is the Business CaseA document that justifies the project showing costs benefits and risks used for decision making
What is the PIDProject Initiation Documentation is the baseline document that defines what the project will deliver and how it will be managed
What is the Project BriefA short document used to authorize initiation containing project outline objectives and constraints
Which process confirms formal acceptance and lessons learnedClosing a Project
Which process handles acceptance of Work PackagesManaging Product Delivery
Which process manages day to day delivery of workControlling a Stage
Which process prepares the Next Stage PlanManaging a Stage Boundary
Which process prepares the PIDInitiating a Project
Who authorizes stages and project closureThe Project Board under the Directing a Project process

About the Flashcards

Flashcards for the PRINCE2 7 Foundation exam provide concise review of the core project management processes and key documents used across the lifecycle. Cards summarize objectives, main activities, transition points and responsibility roles for processes such as Start Up a Project, Initiating a Project, Controlling a Stage, Managing Product Delivery, Managing a Stage Boundary, Directing a Project and Closing a Project.

Use the deck to refresh terminology, definitions and management products - Project Brief, Project Initiation Documentation (PID), Work Packages, Business Case, Highlight/End/Exception reports - and to practice identifying which process produces or authorizes each deliverable. Ideal for quick recall of concepts, reporting lines and decision points tested on the exam.

Topics covered in this flashcard deck:

  • Start Up a Project
  • Initiating a Project
  • Controlling a Stage
  • Managing Product Delivery
  • Managing a Stage Boundary
  • Key management products