Bash, the Crucial Exams Chat Bot
AI Bot

Key Formulas and Calculations  Flashcards

CAPM Flashcards

Break-Even = Fixed Costs ÷ (Price per Unit - Variable Cost per Unit)
Float Calculation
Float = Late Start - Early Start or Float = Late Finish - Early Finish
Estimate to Complete (ETC) Formula
PV = FV ÷ (1 + r)^n
Longest Path with Zero Slack
Critical Path Calculation
To-Complete Performance Index (TCPI) Formula (BAC-based)
Present Value (PV) Formula
TCPI = (BAC - EV) ÷ (BAC - AC)
Break-Even Point Formula
ETC = EAC - AC
FrontBack
Break-Even Point FormulaBreak-Even = Fixed Costs ÷ (Price per Unit - Variable Cost per Unit)
Cost Performance Index (CPI) FormulaCPI = EV ÷ AC
Cost Variance (CV) FormulaCV = EV - Actual Cost (AC)
Critical Path CalculationLongest Path with Zero Slack
Earned Value (EV) FormulaEV = % Complete × Budget at Completion (BAC)
Estimate at Completion (EAC) Formula (CPI-based)EAC = BAC ÷ CPI
Estimate to Complete (ETC) FormulaETC = EAC - AC
Expected Activity Duration Formula (PERT)Expected Duration = (Optimistic + 4 × Most Likely + Pessimistic) ÷ 6
Float CalculationFloat = Late Start - Early Start or Float = Late Finish - Early Finish
Future Value (FV) FormulaFV = PV × (1 + r)^n
Number of Communication Channels FormulaChannels = n(n-1)/2
Point of Total Assumption (PTA) FormulaPTA = Target Cost + (Ceiling Price - Target Price) ÷ Buyer’s Share Ratio
Present Value (PV) FormulaPV = FV ÷ (1 + r)^n
Risk Probability and Impact Matrix CalculationRisk Score = Probability × Impact
Schedule Performance Index (SPI) FormulaSPI = EV ÷ PV
Schedule Variance (SV) FormulaSV = EV - Planned Value (PV)
Standard Deviation (SD) FormulaSD = (Pessimistic - Optimistic) ÷ 6
To-Complete Performance Index (TCPI) Formula (BAC-based)TCPI = (BAC - EV) ÷ (BAC - AC)
To-Complete Performance Index (TCPI) Formula (EAC-based)TCPI = (BAC - EV) ÷ (EAC - AC)
Variance at Completion (VAC) FormulaVAC = BAC - EAC
Front
Cost Performance Index (CPI) Formula
Click the card to flip
Back
CPI = EV ÷ AC
Front
Point of Total Assumption (PTA) Formula
Back
PTA = Target Cost + (Ceiling Price - Target Price) ÷ Buyer’s Share Ratio
Front
Estimate to Complete (ETC) Formula
Back
ETC = EAC - AC
Front
Schedule Variance (SV) Formula
Back
SV = EV - Planned Value (PV)
Front
Break-Even Point Formula
Back
Break-Even = Fixed Costs ÷ (Price per Unit - Variable Cost per Unit)
Front
Expected Activity Duration Formula (PERT)
Back
Expected Duration = (Optimistic + 4 × Most Likely + Pessimistic) ÷ 6
Front
Standard Deviation (SD) Formula
Back
SD = (Pessimistic - Optimistic) ÷ 6
Front
Future Value (FV) Formula
Back
FV = PV × (1 + r)^n
Front
To-Complete Performance Index (TCPI) Formula (BAC-based)
Back
TCPI = (BAC - EV) ÷ (BAC - AC)
Front
Estimate at Completion (EAC) Formula (CPI-based)
Back
EAC = BAC ÷ CPI
Front
Number of Communication Channels Formula
Back
Channels = n(n-1)/2
Front
To-Complete Performance Index (TCPI) Formula (EAC-based)
Back
TCPI = (BAC - EV) ÷ (EAC - AC)
Front
Critical Path Calculation
Back
Longest Path with Zero Slack
Front
Risk Probability and Impact Matrix Calculation
Back
Risk Score = Probability × Impact
Front
Present Value (PV) Formula
Back
PV = FV ÷ (1 + r)^n
Front
Earned Value (EV) Formula
Back
EV = % Complete × Budget at Completion (BAC)
Front
Cost Variance (CV) Formula
Back
CV = EV - Actual Cost (AC)
Front
Schedule Performance Index (SPI) Formula
Back
SPI = EV ÷ PV
Front
Variance at Completion (VAC) Formula
Back
VAC = BAC - EAC
Front
Float Calculation
Back
Float = Late Start - Early Start or Float = Late Finish - Early Finish
1/20
This deck focuses on essential formulas for cost, time, quality, and risk management, such as Earned Value Management (EVM), Critical Path Method (CPM), and communication channels calculation.
Share on...
Follow us on...