PMP Common Acronyms Flashcards
Front | Back |
ES | Early Start |
LF | Late Finish |
WPI | Work Performance Information |
BCR | Benefit-Cost Ratio |
EAC | Estimate at Completion |
RACI | Responsible; Accountable; Consulted; Informed |
NDA | Non-Disclosure Agreement |
LRC | Learning Resource Center |
LS | Late Start |
WBS | Work Breakdown Structure |
TOR | Terms of Reference |
VAC | Variance at Completion |
PDM | Precedence Diagramming Method |
PV | Planned Value |
PMBOK | Project Management Body of Knowledge |
EV | Earned Value |
ROI | Return on Investment |
CV | Cost Variance |
ETC | Estimate to Complete |
PMO | Project Management Office |
PERT | Program Evaluation and Review Technique |
SV | Schedule Variance |
CCB | Change Control Board |
CPI | Cost Performance Index |
RBS | Resource Breakdown Structure |
PMP | Project Management Professional |
VOIP | Voice Over Internet Protocol |
CSF | Critical Success Factor |
AC | Actual Cost |
EF | Early Finish |
BPR | Business Process Reengineering |
PB | Performance Baseline |
TCO | Total Cost of Ownership |
SPI | Schedule Performance Index |
WPR | Work Performance Reports |
SDLC | System Development Life Cycle |
CCB | Change Control Board |
RFI | Request for Information |
AOB | Any Other Business |
WPD | Work Performance Data |
SIPOC | Suppliers; Inputs; Process; Outputs; Customers |
FPA | Function Point Analysis |
MVP | Minimum Viable Product |
TTT | Train-the-Trainer |