PMI Project Management Professional Practice Question

You are managing a project under a fixed-price incentive fee contract with a ceiling price of $1,200,000, a target cost of $1,000,000, and a target price of $1,100,000. If the buyer's share ratio is 80/20, what is the Point of Total Assumption (PTA)?

  • $1,000,000

  • $1,025,000

  • $1,500,000

  • $1,125,000

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot