PMI Project Management Professional Practice Question
In PERT estimation, if an activity has an optimistic duration of 3 days, a most likely duration of 5 days, and a pessimistic duration of 13 days, the Expected Duration (TE) is 6 days.
True
False
In PERT estimation, if an activity has an optimistic duration of 3 days, a most likely duration of 5 days, and a pessimistic duration of 13 days, the Expected Duration (TE) is 6 days.
True
False
In PERT estimation, the expected duration (TE) is calculated by taking an average of three estimates: the optimistic, the most likely, and the pessimistic. The most likely duration gets more weight because it's the most probable.
Here’s how it works:
So, the expected duration (TE) is 6 days. This method balances all the estimates while giving more weight to the most likely one.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All plans include the following perks.
Our pricing is simple. Full access to all certifications and exams, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
No annoying ads and popups. Study without distractions.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even more discounts than before.
Unlimited access to all PBQs and be prepared for the real thing.
Create an account or sign in to access our study materials.