PMI Project Management Professional Practice Question
During the quantitative risk analysis phase, what does a Decision Tree Analysis primarily help to determine?
It calculates the Expected Monetary Values (EMVs) for different possible scenarios assisting in choosing the optimal decision path.
It determines the degree of consensus achieved in a Delphi Technique.
It identifies the sequence of scheduled activities in the critical path method.
It indicates the interdependencies of project tasks within a Work Breakdown Structure (WBS).