PMI Project Management Professional Practice Question

During the procurement planning stage of a Waterfall project, which aspect is most critical for the project manager to align with the organization's financial systems and legal requirements?

  • Identifying procurement strategy aspects such as project delivery methods, contract types, and procurement phases.

  • Focusing exclusively on the speed of procurement processes to accelerate project delivery.

  • Prioritizing procurement activities based solely on the availability of procurement resources.

  • Assessing only the technical capabilities of potential sellers to ascertain their fit for the project.

PMI Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot