Project Management Professional Practice Question

During a qualitative risk analysis meeting, the project manager organizes a risk workshop with key project stakeholders. What is the PRIMARY purpose of conducting a risk workshop?

  • To develop an initial understanding of each identified risk's probability, impact, and determine appropriate prioritization for further analysis or action

  • To create a detailed project schedule including all identified risks and their corresponding response actions

  • To transfer ownership of project risks to the stakeholders attending the workshop

  • To assign budget allocations to each identified risk based on cost impact

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot