During a facility upgrade project, your team is scheduled to install a backup power sub-panel. The network diagram indicates that this activity has no predecessors other than project start, giving it an Early Start (ES) of the morning of Day 5. The electricians estimate the task will require 4 full, consecutive workdays. Senior management has asked you to confirm the earliest calendar day materials will be freed for the next task. Using a forward-pass calculation that treats Day numbers inclusively (EF = ES + Duration − 1), what Early Finish (EF) date should you report?

  • Day 7

  • Day 8

  • Day 6

  • Day 9

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot