An agile team has just completed its fifth sprint. While they are consistently delivering work, sprint reviews reveal frequent stakeholder surprises and dipping team morale due to rework. The project manager wants to address the root causes of these issues. Which of the following actions should the project manager facilitate first to foster a culture of continuous improvement?

  • A meeting with key stakeholders to realign on the project vision and roadmap.

  • More detailed process documentation to ensure alignment on sprint goals.

  • A formal change request process to better manage stakeholder expectations.

  • A sprint retrospective for the team to inspect its process and create an improvement plan.

Project Management Professional
Agile
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot