Project Management Professional Practice Question

A scheduling analyst is performing a forward pass on the project network diagram. One activity is scheduled to begin at the start of Day 5 and has a planned duration of four working days, with no non-working time in between. Based on standard CPM conventions, on which calendar day should the analyst record the activity's Early Finish value?

  • Day 8

  • Day 9

  • Day 10

  • Day 7

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot