Project Management Professional Practice Question

A project to develop a new customer relationship management (CRM) system is nearing completion. Quality testing is complete, stakeholders concur that all requirements have been met, and the team is preparing to close out the work. To ensure the project or phase is closed properly, what is the BEST action the project manager should take next?

  • Begin the next project.

  • Release all project team members and inform stakeholders that the project is completed.

  • Conduct a final project performance report review and obtain formal acceptance of the project deliverables from the customer.

  • Archive all project documents.

Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot