PMI Project Management Professional Practice Question

A project manager is considering various contract types for a new software development project. Which of the following contract types transfers the highest risk to the seller?

  • Cost Plus Fixed Fee (CPFF)

  • Fixed Price Incentive Fee (FPIF)

  • Firm Fixed Price (FFP)

  • Time and Materials (T&M)