PMI Project Management Professional Practice Question
A project manager is considering various contract types for a new software development project. Which of the following contract types transfers the highest risk to the seller?
Cost Plus Fixed Fee (CPFF)
Fixed Price Incentive Fee (FPIF)
Firm Fixed Price (FFP)
Time and Materials (T&M)