Which of the following artifacts in a predictive, plan-based project is used to record and track identified risks, their analysis, and planned responses?
Issue Log
Daily Stand-up Meeting Notes
Risk Register
Product Backlog
Which of the following artifacts in a predictive, plan-based project is used to record and track identified risks, their analysis, and planned responses?
Issue Log
Daily Stand-up Meeting Notes
Risk Register
Product Backlog
The Risk Register is a key artifact in predictive, plan-based projects that documents all identified risks, their assessment in terms of impact and probability, and the response strategies. It helps in monitoring and controlling risks throughout the project. An Issue Log records problems that are currently occurring, not potential future risks. The Product Backlog and Daily Stand-up Meeting Notes are artifacts used in agile methodologies, not typically in predictive, plan-based projects.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.