The quality management plan defines the process for managing changes to the project scope.
True
False
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Bash, the Crucial Exams Chat Bot
AI Bot
The quality management plan defines the process for managing changes to the project scope.
True
False
This statement is false because the quality management plan outlines how quality policies will be implemented to meet the project's quality requirements. It includes quality standards, objectives, roles, and responsibilities related to quality management. The process for managing changes to the project scope is documented in the scope management plan, not the quality management plan.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.