CAPM Practice Question
In a project schedule, activities with zero total float are considered non-critical.
True
False
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Bash, the Crucial Exams Chat Bot
AI Bot
In a project schedule, activities with zero total float are considered non-critical.
True
False
In the Critical Path Method, activities with zero total float are critical activities. They form the project's critical path, and any delay in these activities directly affects the project's completion date. Therefore, activities with zero total float are considered critical, not non-critical.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.