CAPM Practice Question
An activity that marks the completion of a major phase in a project schedule typically has a significant duration to accommodate necessary tasks.
True
False
An activity that marks the completion of a major phase in a project schedule typically has a significant duration to accommodate necessary tasks.
True
False
This statement is false. Milestones represent significant points or events in a project schedule and are used to mark the completion of major phases or deliverables. They have zero duration because they do not encompass actual work or tasks; instead, they signify the point in time when certain objectives have been achieved. Tasks or activities, on the other hand, require time and resources to complete and thus have a defined duration.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.