A project manager wants to identify which activities, if delayed, will delay the entire project's completion date. Which technique should the project manager use to find these activities?
Perform risk analysis to identify high-risk activities.
Conduct a cost-benefit analysis on all project activities.
Use Critical Path Method to identify critical activities.
Apply resource leveling to adjust activity schedules.