A project manager wants to identify which activities, if delayed, will delay the entire project's completion date. Which technique should the project manager use to find these activities?

  • Perform risk analysis to identify high-risk activities.

  • Conduct a cost-benefit analysis on all project activities.

  • Use Critical Path Method to identify critical activities.

  • Apply resource leveling to adjust activity schedules.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot