CAPM Practice Question
A burndown chart an artifact used in predictive, plan-based projects to track project progress.
False
True
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Bash, the Crucial Exams Chat Bot
AI Bot
A burndown chart an artifact used in predictive, plan-based projects to track project progress.
False
True
Burndown charts are primarily used in agile methodologies to visualize the remaining work in a sprint or iteration. In predictive, plan-based projects, progress is typically tracked using tools like Gantt charts or project schedules. Therefore, a burndown chart is not an artifact used in predictive, plan-based projects.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.