CompTIA Project+ PK0-005 (V5) Practice Question

While reviewing the six-month rollout plan for an enterprise Wi-Fi upgrade, a project manager must flag any schedule activities that have zero float so that even a one-day slip will move the final go-live milestone. Which of the following techniques is the BEST way to pinpoint these time-sensitive activities?

  • Analyze the critical path

  • Implement fast-tracking on activities

  • Perform a qualitative risk analysis

  • Use resource smoothing techniques

CompTIA Project+ PK0-005 (V5)
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

SAVE $47
$390.00 $343.00
Bash, the Crucial Exams Chat Bot
AI Bot